This month saw strong progress on site, with works transitioning from excavation into the early stages of building structure. Detailed foundation works are underway, with shear walls, precast panels and columns installed, and preparations in place for the ground slab. Drainage works are nearing completion, the first ground slab pour has been completed, and permanent mains power is now connected, enabling the tower crane and site facilities to operate efficiently as construction advances.